Loading...
Belarus: Strominvest II-02
Issues
Community health and safety
Description: Complaint raises concerns related to public health and safety including incidents of or an increase in accidents, release of hazardous materials, and spread of diseases. Concerns related to retaliation and/or violence are not included.
Complaints with this Issue: 373
Sectors
Infrastructure
Description: Project relates to construction or improvement of large structures, facilities, or public works projects. Examples include roads and other transportation projects, sanitation and water treatment facilities, power plants, and industrial facilities.
Complaints in this Sector: 1183
Complaint
IAM: Compliance Advisor/Ombudsman (CAO)
ID: FY22/01
Date Filed: July 29, 2021
Date Closed: Aug. 18, 2021
Status: Closed Without Outputs
Description
Complaint Stages
Filing
July 29, 2021
Filing
Status:
Start Date: July 29, 2021
Registration
Not Undertaken
Registration
Status: Not Undertaken
Explanation: Not offered by mechanism, Stage is not practiced by mechanism
Eligibility
July 29, 2021 -
Aug. 18, 2021
Eligibility
Status: Closed With Output
Explanation: Forwarded to other body within bank; Inadequate information, Early-stage project
Dispute Resolution
Not Undertaken
Dispute Resolution
Status: Not Undertaken
Explanation: Case closed in earlier stage, Complaint was originally found ineligible or not registered
Compliance Review
Not Undertaken
Compliance Review
Status: Not Undertaken
Explanation: Case closed in earlier stage, Complaint was originally found ineligible or not registered
Has Compliance Report: No
Non-Compliance Found: No
Monitoring
Not Undertaken
Monitoring
Status: Not Undertaken
Explanation: Case closed in earlier stage, Complaint was originally found ineligible or not registered
Closed
Aug. 18, 2021
Timeline