Loading...
Empresa Electrica Pangue S.A.-02/Upper Bio-Bio Watershed
Issues
Biodiversity
Description: Complaint raises concerns about impacts on plant or animal species in the natural environment.
Complaints with this Issue: 137
Community health and safety
Description: Complaint raises concerns related to public health and safety including incidents of or an increase in accidents, release of hazardous materials, and spread of diseases. Concerns related to retaliation and/or violence are not included.
Complaints with this Issue: 373
Consultation and disclosure
Description: Complaint raises concerns regarding inadequate or absent consultation about or disclosure of project information, including project impacts and/or mitigation plans.
Complaints with this Issue: 550
Displacement (physical and/or economic)
Description: Complaint raises concerns about physical relocation, loss of shelter, and/or loss of assets that relate to income or livelihood.
Complaints with this Issue: 516
Due diligence
Description: Complaint raises concerns about inadequate or absent prior investigation of project impacts.
Complaints with this Issue: 484
Environmental
Description: Complaint raises concerns regarding environmental impacts that do not refer specifically to water, pollution, or biodiversity.
Complaints with this Issue: 414
Indigenous peoples
Description: Complaint raises concerns about impacts on indigenous or traditional communities.
Complaints with this Issue: 92
Sectors
Energy
Description: Project relates to energy access, legal frameworks regarding the energy sector, and development and operation of energy infrastructure, including power generation and electric and gas distribution and storage. Projects specifically related to the extraction of oil and gas are not included.
Complaints in this Sector: 389
Infrastructure
Description: Project relates to construction or improvement of large structures, facilities, or public works projects. Examples include roads and other transportation projects, sanitation and water treatment facilities, power plants, and industrial facilities.
Complaints in this Sector: 1183
Project
Name: Empresa Electrica Pangue S.A.-02/Upper Bio-Bio Watershed
Investments: IFC/MIGA 2067
Client:
Country: Chile
Complaint
IAM: Compliance Advisor/Ombudsman (CAO)
ID: chile-empresa-electrica-pangue-sa-02upper-bio-bio-
Date Filed: July 1, 2002
Date Closed: June 30, 2010
Status: Closed With Outputs
Description
Complaint Stages
Filing
July 1, 2002
Filing
Status:
Start Date: July 1, 2002
Registration
Not Undertaken
Registration
Status: Not Undertaken
Explanation: Not offered by mechanism, Stage is not practiced by mechanism
Eligibility
July 1, 2002 -
May 1, 2003
Eligibility
Status: Closed With Output
Start Date: July 1, 2002
End Date: May 1, 2003
Dispute Resolution
May 1, 2003 -
March 1, 2006
Dispute Resolution
Status: Closed With Output
Start Date: May 1, 2003
End Date: March 1, 2006
Compliance Review
Not Undertaken
Compliance Review
Status: Not Undertaken
Explanation: Case closed in earlier stage
Has Compliance Report: No
Non-Compliance Found: No
Monitoring
March 1, 2006 -
June 30, 2010
Monitoring
Status: Closed With Output
Start Date: March 1, 2006
End Date: June 30, 2010