Mumbai Urban Transport Project (Second Request)
Issues
Consultation and disclosure
Description: Complaint raises concerns regarding inadequate or absent consultation about or disclosure of project information, including project impacts and/or mitigation plans.
Complaints with this Issue: 550
Displacement (physical and/or economic)
Description: Complaint raises concerns about physical relocation, loss of shelter, and/or loss of assets that relate to income or livelihood.
Complaints with this Issue: 516
Due diligence
Description: Complaint raises concerns about inadequate or absent prior investigation of project impacts.
Complaints with this Issue: 484
Sectors
Infrastructure
Description: Project relates to construction or improvement of large structures, facilities, or public works projects. Examples include roads and other transportation projects, sanitation and water treatment facilities, power plants, and industrial facilities.
Complaints in this Sector: 1183
Description
Complaint Stages
Filing
June 24, 2004
Filing
Status:
Start Date: June 24, 2004
Registration
June 24, 2004 -
June 29, 2004
Registration
Status: Closed With Output
Start Date: June 24, 2004
End Date: June 29, 2004
Eligibility
June 29, 2004 -
Sept. 3, 2004
Eligibility
Status: Closed With Output
Start Date: June 29, 2004
End Date: Sept. 3, 2004
Dispute Resolution
Not Undertaken
Dispute Resolution
Status: Not Undertaken
Explanation: Not offered by mechanism, Dispute resolution was not an option in this case; Not offered by mechanism, Stage is not practiced by mechanism
Compliance Review
Sept. 3, 2004 -
Dec. 21, 2005
Compliance Review
Status: Closed With Output
Start Date: Sept. 3, 2004
End Date: Dec. 21, 2005
Has Compliance Report: Yes
Non-Compliance Found: Yes
Monitoring
Closed With Output
Monitoring
Status: Closed With Output
Start Date: None
Closed
Not Closed
Timeline
Involved Groups
Name | Complaints | Group Type |
---|---|---|
The Hanuman Welfare Society (HWS), the Gazi Nagar Sudhar Samiti (GNSS) and the Jai Hanuman Rahiwasi Sewa Sangh (JHRSS) | 1 | Local CSO |
Related Complaints
Project | IAM | Country | Date Filed | Status |
---|---|---|---|---|
Mumbai Urban Transport Project | WB Panel | India | 28/04/2004 | Closed With Outputs |