Pakistan: Karot Hydro-05/Jhelum River
Issues
Displacement (physical and/or economic)
Description: Complaint raises concerns about physical relocation, loss of shelter, and/or loss of assets that relate to income or livelihood.
Complaints with this Issue: 516
Environmental
Description: Complaint raises concerns regarding environmental impacts that do not refer specifically to water, pollution, or biodiversity.
Complaints with this Issue: 414
Sectors
Energy
Description: Project relates to energy access, legal frameworks regarding the energy sector, and development and operation of energy infrastructure, including power generation and electric and gas distribution and storage. Projects specifically related to the extraction of oil and gas are not included.
Complaints in this Sector: 389
Infrastructure
Description: Project relates to construction or improvement of large structures, facilities, or public works projects. Examples include roads and other transportation projects, sanitation and water treatment facilities, power plants, and industrial facilities.
Complaints in this Sector: 1183
Project
Name: Karot Hydro
Investments: IFC/MIGA 36008
Client: Karot Power Company Limited (KPCL)
Support: Loans
Country: Pakistan
Complaint
IAM: Compliance Advisor/Ombudsman (CAO)
ID: FY22/18
Date Filed: June 20, 2022
Date Closed: July 22, 2022
Status: Active
Description
Complaint Stages
Filing
June 20, 2022
Filing
Status:
Start Date: June 20, 2022
Registration
Not Undertaken
Registration
Status: Not Undertaken
Explanation: Not offered by mechanism, Stage is not practiced by mechanism
Eligibility
June 20, 2022 -
July 22, 2022
Eligibility
Status: Closed With Output
Start Date: June 20, 2022
End Date: July 22, 2022
Dispute Resolution
Not Undertaken
Dispute Resolution
Status: Not Undertaken
Explanation: Forwarded to other body within bank; Addressed outside process, Management is addressing or has addressed concerns
Compliance Review
Not Undertaken
Compliance Review
Status: Not Undertaken
Explanation: Forwarded to other body within bank; Addressed outside process, Management is addressing or has addressed concerns
Has Compliance Report: No
Non-Compliance Found: No
Monitoring
Not Undertaken
Closed
July 22, 2022
Timeline