Peshawar Sustainable Bus Rapid Transit Corridor Project
Issues
Community health and safety
Description: Complaint raises concerns related to public health and safety including incidents of or an increase in accidents, release of hazardous materials, and spread of diseases. Concerns related to retaliation and/or violence are not included.
Complaints with this Issue: 373
Displacement (physical and/or economic)
Description: Complaint raises concerns about physical relocation, loss of shelter, and/or loss of assets that relate to income or livelihood.
Complaints with this Issue: 516
Sectors
Infrastructure
Description: Project relates to construction or improvement of large structures, facilities, or public works projects. Examples include roads and other transportation projects, sanitation and water treatment facilities, power plants, and industrial facilities.
Complaints in this Sector: 1183
Project
Name: Peshawar Sustainable Bus Rapid Transit Corridor Project
Investments: ADB 48289-002
Client:
Support: Loans
Country: Pakistan
Complaint
IAM: Special Project Facilitator and Compliance Review Panel (SPF CRP)
Date Filed: Sept. 28, 2020
Date Closed: Jan. 19, 2022
Description
Complaint Stages
Filing
Sept. 28, 2020
Filing
Status:
Start Date: Sept. 28, 2020
Registration
Sept. 28, 2020 -
Dec. 15, 2020
Registration
Status: Closed With Output
Start Date: Sept. 28, 2020
End Date: Dec. 15, 2020
Eligibility
Dec. 15, 2020 -
Jan. 14, 2021
Eligibility
Status: Closed With Output
Explanation: Addressed outside process; Addressed outside process, Management is addressing or has addressed concerns
Dispute Resolution
Not Undertaken
Dispute Resolution
Status: Not Undertaken
Explanation: Case closed in earlier stage; Case closed in earlier stage, Complaint was originally found ineligible or not registered
Compliance Review
Not Undertaken
Compliance Review
Status: Not Undertaken
Explanation: Case closed in earlier stage; Case closed in earlier stage, Complaint was originally found ineligible or not registered
Has Compliance Report: No
Non-Compliance Found: No
Monitoring
Not Undertaken
Monitoring
Status: Not Undertaken
Explanation: Case closed in earlier stage; Case closed in earlier stage, Complaint was originally found ineligible or not registered
Closed
Jan. 19, 2022
Timeline
Related Complaints