Loading...
Third Power Project, Fourth Power Project, and proposed Bujagali Hydropower Project
Issues
Community health and safety
Description: Complaint raises concerns related to public health and safety including incidents of or an increase in accidents, release of hazardous materials, and spread of diseases. Concerns related to retaliation and/or violence are not included.
Complaints with this Issue: 373
Consultation and disclosure
Description: Complaint raises concerns regarding inadequate or absent consultation about or disclosure of project information, including project impacts and/or mitigation plans.
Complaints with this Issue: 550
Displacement (physical and/or economic)
Description: Complaint raises concerns about physical relocation, loss of shelter, and/or loss of assets that relate to income or livelihood.
Complaints with this Issue: 516
Due diligence
Description: Complaint raises concerns about inadequate or absent prior investigation of project impacts.
Complaints with this Issue: 484
Livelihoods
Description: Complaint raises concerns about impacts on the means by which people make a living, including wage-based income, trade and bartering, agriculture, fishing, foraging, and other natural-resource based means.
Complaints with this Issue: 362
Sectors
Conservation and environmental protection
Description: Project relates to preservation or management of the natural environment, legal frameworks regarding environmental protection or pollution, and carbon sequestration or other climate change mitigation activities.
Complaints in this Sector: 66
Energy
Description: Project relates to energy access, legal frameworks regarding the energy sector, and development and operation of energy infrastructure, including power generation and electric and gas distribution and storage. Projects specifically related to the extraction of oil and gas are not included.
Complaints in this Sector: 389
Infrastructure
Description: Project relates to construction or improvement of large structures, facilities, or public works projects. Examples include roads and other transportation projects, sanitation and water treatment facilities, power plants, and industrial facilities.
Complaints in this Sector: 1183
Project
Name: Third Power Project, Fourth Power Project, and proposed Bujagali Hydropower Project
Investments: WB
Client:
Support: Loans
Country: Uganda
Complaint Stages
Filing
July 27, 2001
Filing
Status:
Start Date: July 27, 2001
Registration
July 27, 2001 -
Aug. 7, 2001
Registration
Status: Closed With Output
Start Date: July 27, 2001
End Date: Aug. 7, 2001
Eligibility
Aug. 7, 2001 -
Oct. 10, 2001
Eligibility
Status: Closed With Output
Start Date: Aug. 7, 2001
End Date: Oct. 10, 2001
Dispute Resolution
Not Undertaken
Dispute Resolution
Status: Not Undertaken
Explanation: Not offered by mechanism, Dispute resolution was not an option in this case
Compliance Review
Oct. 10, 2001 -
June 7, 2002
Compliance Review
Status: Closed With Output
Start Date: Oct. 10, 2001
End Date: June 7, 2002
Has Compliance Report: Yes
Non-Compliance Found: Yes
Monitoring
Not Undertaken
Monitoring
Status: Not Undertaken
Explanation: Mechanism deemed involvement unnecessary, Mechanism chose not to monitor
Closed
June 7, 2002
Timeline
Documents
Involved Groups
Commitments