Loading...
Project Information
Investment ID: Loan 3365-IND
Bank: Asian Development Bank
Environmental Category: B
Country: India
Region: South Asia
Approval Date: Dec. 9, 2015
Investment Types: Loans
Total Project Cost: USD 2.6 billion
Total Complaints: 1
Description
The project will fund electric transmission system investments in India, including (i) a portion of the Government of India's "'Green Energy Corridor" initiative to facilitate the transfer of power from the renewable energy (RE) rich areas to other parts of the country, consisting of 765 kilovolt (kV) and 400 kV high voltage transmission lines and an associated 765/400kV substation and associated equipment, and (ii) four high voltage direct current (HVDC) terminals (two at 800 kV and two at 320 kV) as part of increased inter-regional connectivity between India's western and southern regional power grids.
Investments
Investment Type | ID | Amount | Status | Bank | Client |
---|---|---|---|---|---|
Loans | Loan 3365-IND | USD 500.0 million | Planned | ADB |
Related Complaints
Asian Development Bank SPF CRP Complaints | IAM | Country | Date Filed | Status |
---|---|---|---|---|
Green Energy Corridor and Grid Strengthening Project | ADB SPF CRP | India | 24/05/2019 | Closed Without Outputs |
Implementers
Name | Complaints | Dispute Resolutions | DR Successful | Compliance Reviews | Non-Compliance |
---|---|---|---|---|---|
Power Grid Corporation of India Limited |